Minister of Electricity Kgosientsho Ramokgopa wants to take a hands-off approach when working with Eskom, despite recommendations from the VGBE Consortium’s “Operation Assessment Report” on the power utility’s need for external expertise.
The VGBE report, commissioned by the National Treasury a year ago, suggested that external professionals could help restore Eskom to operational health.
However, Ramokgopa maintains that the decision to utilise such expertise rests with Eskom’s management and board.
“I won’t overstep my bounds,” he declared during a media briefing on Monday. “The choice of whether or not they need additional external help lies with them.”
The report, released earlier this month, followed site visits and research by members of the four organisations involved. It exposed Eskom’s critical state, citing poor management, leadership, and employee morale impacted by uncertainty and a lack of incentives.
Among their recommendations, the VGBE Consortium called for the implementation of an external expert team to work with Eskom for a period of one and a half to two years.
The consortium also advised running an analysis and forensic review of Eskom’s accounting methods and financial management practices.
Additionally, they emphasised the importance of continuous improvement through international knowledge exchange and best practices in unbundling electricity markets.
Furthermore, the report recommended a lifetime-extension study for specific power plants, including Arnot, Camden, Grootvlei, Hendrina and Matla.
Ramokgopa repeated his intention to avoid interfering with Eskom’s management and voiced confidence in the board’s ability to fulfil its responsibilities.
“Their primary goal is to safeguard Eskom’s interests,” he stated. “Over the past months, we’ve established a collaborative platform where everyone understands their role, which streamlines processes.
“We urge Eskom’s employees to stay on and contribute to overcoming the utility’s challenges.”
The minister acknowledged that some recommendations are already being addressed. The Treasury has reportedly relaxed procurement requirements to expedite the process.
“Outage budgeting allocation has improved,” Ramokgopa noted. “We’re seeing signs of better outage preparedness, progress with Medupi, and the implementation of coal stockpiling and rain readiness programmes.”
He identified Duvha, Kendal, Kusile, Majuba, Matla and Tutuka power stations as significant contributors to unplanned load shedding. Improvements at these stations, he concluded, would lead to substantial overall improvement.
Pictured above: Minister of Electricity Kgosientsho Ramokgopa.