Eskom to fast-track feeding green energy to the grid

By
N5
3 Min Read
LANGUAGE:

By Doreen Mokgolo

The Energy Availability Factor improved from 57% at the beginning of the year to 61.9% from 14 October to 17 October – a 4.9% improvement.

The minister of Electricity and Energy, Kgosientsho Ramokgopa, revealed this during a media briefing on the Independent Power Producer Programme in Tshwane on Monday.

As part of the programme, the department plans to introduce more green energy to the national power grid in the next four weeks.

Green energy is expected to reduce carbon emissions by 350 to 420 million tons annually.

The minister said the country is entering the next generation of battery energy storage, which will allow the use of excess capacity to power batteries.

“The batteries are for storage so that we can have a backup when we don’t have the sun or wind, especially during peak hours.”

Ramokgopa said that since its implementation in 2011, there have been nine bid windows for green energy projects with a capacity of 8,231 megawatts currently in the market. 

“There are 1,897 megawatts in construction from 17 projects, most of which are set in Cape Town.

“We would like to expand to other provinces; as it stands, KZN doesn’t have any renewable energy projects,” he said.

Meanwhile, the country has not experienced load shedding in 208 days.

“For the financial year to date, the 1 April-17 October unplanned capacity loss factor is at 25.5%, improving from 33.79% in the corresponding period last year. This represents an 8.3% improvement.

“The unplanned outages of the generation units averaged 10,508 megawatts during the past seven days as compared to 15,605 megawatts in the corresponding week last year,” he said.

The improved performance is credited to the implemented maintenance at the Duvha, Kusile, and other power stations.

The minister said ongoing planned maintenance is at 5,798 megawatts, aligning with the summer maintenance strategy.

Kusile Unit Six and Koeberg Unit Two are expected to be completed by December, and Medupi Unit Four will be completed by the end of March.

“This will further increase the reliability of the stations in preparation for winter 2025 and beyond,” he said.

Pictured above: Minister of Electricity and Energy Kgosientsho Ramokgopa.